Main contractor and project manager for consent management, demolition and decontamination.
Outline of Work
- Resource consent (sub-division and land-use) for residential subdivision and development. The Resource Consent consisted of:
- Public Stormwater Extension
- Sanitary Sewer public line bridging.
- Project Management
- Engineering approval for public drainage works
- Building consent consisted of:
- 1 x double level dwelling
- Double internal garage
- 4-bedroom open plan living area
Timeline
Total Duration: 4 months
Project commenced in late 2015 and was completed successfully in early 2016.