778 Great South Road, Penrose
Main contractor and project manager from concept to completion
Outline of Work
- Building and Resource Consent
- Engineering Approval for all public drainage
- New Vehicle Crossings
- Public walkway and footpath
- Installation of pumps and tanks for new service station
- New driveways, convenience store, fitouts
- Car wash
- Pylon signage and canopy refurbishment
Timeline
Total Duration: 16 months
Project commenced in May 2012 and was successfully completed in Aug 2013.